Jump to content

Templin Solar Park

Coordinates: 53°02′N 13°32′E / 53.03°N 13.54°E / 53.03; 13.54
From Wikipedia, the free encyclopedia
Templin Solar Park
Map
CountryGermany
LocationTemplin, Uckermark, Brandenburg
Coordinates53°02′N 13°32′E / 53.03°N 13.54°E / 53.03; 13.54
StatusOperational
Commission date30 September 2012
Construction cost€205 million[1]
OwnerCommerz Real
Solar farm
TypeFlat-panel PV
Site area214 ha[2]
Power generation
Units operational1,500,000
Nameplate capacity128.48 MW

Templin Solar Park is a 128 megawatt (MW) photovoltaic power station, located at the former Templin military airport.[3]

History

[edit]

The plant was built between 5 June and 30 September 2012. The electrical connection to the 110 kV network, via two substations operated by e.dis AG, was made in April 2013. The plant covers an area of approximately 214 ha. It consists of 1.5 million thin-film modules from the manufacturer First Solar from its factory in Frankfurt (Oder). The 114 power inverters used were supplied by German company SMA. The park was built by Bavarian company Belectric. The construction costs were €204.5 million and about 500 people were employed during its fabrication.