Glenwood Generating Station
Glenwood Generating Station | |
---|---|
Country | United States |
Location | Glenwood Landing, Long Island, New York |
Coordinates | 40°49′39″N 73°38′51″W / 40.82750°N 73.64750°W |
Status | In service |
Power generation | |
Nameplate capacity |
|
External links | |
Commons | Related media on Commons |
Glenwood Generating Station is a power station in Glenwood Landing, New York owned by National Grid USA. It is mainly known for being the former site of an architecturally significant 1920s brick power station. That building and an adjacent 1950s station were demolished over the course of 2013 to 2015, due to their obsolescence as well as the excessive cost of safely retaining the building given its poor condition. Four smaller gas turbine peaking generators remain in operation, as does the Y-50 Cable connection across Long Island Sound.
Architecture
[edit]Station 2 was constructed in the 1920s and was considered significant as an example of early 20th-century industrial architecture. It was designed in an industrial Beaux-Arts style, with large arched windows and stringcourse intended to prevent it from becoming an eyesore given its proximity to affluent communities. It was constructed with Flemish bond brickwork and decorative limestone elements.[1][2] It was also constructed to minimize noise and ash pollution. Buildings with such architectural detail were usually found in urban areas, making the Glenwood plant unusual for being far from urban areas at the time of its construction.[3]
The building was divided into three sections: a narrow four-story administration section to the north containing offices; a five-story turbine room containing a large open space with decorated glazed buff brick walls; and a six-story boiler house mainly filled with equipment, topped by six 140-foot smoke stacks (ultimately reaching 265 feet above the floor slab). At the time of its demolition the New York State Office of Parks, Recreation and Historic Preservation determined that it appeared to meet the criteria for listing on the National Register of Historic Places, triggering an alternative use analysis. Given the building's poor condition after three decades of disuse, the excessive cost of making the building structurally sound prevented any plans to retain or renovate it.[1][2]
History
[edit]Construction and early history
[edit]The first facility on the site was Station 1, constructed in 1906 and expanded during World War I, which existed until at least 1939. The Station 2 building was constructed from 1928 to 1931 by the Nassau Power and Light Company, a predecessor of the Long Island Lighting Company (LILCO).[1][2] The extra generating capacity was needed due to a sixfold increase in Long Island's electricity demand from 1910 to 1925. The expansion also reflected LILCO's then-novel philosophy of using few centralized power plants interconnected by transmission lines, rather than many small plants distributed through the region.[3] In 1936 it was described as "the key electric generating plant of the Long Island system,"[4] and its control room managed LILCO's entire system.[3] In 1939 it was upgraded to burn both coal and oil, and in 1946 natural gas capability was added.[1][2]
In 1942, a 3-hour power outage caused by testing of new distribution circuits affected seven major factories producing material for World War II. These included the Grumman plant in Bethpage and the Republic Aviation plant in Farmingdale, where workers staged an impromptu baseball game while they waited for power to return. Local hospitals and Mitchel Field were able to continue operating under auxiliary power.[5] Although sabotage was not suspected, it caused the colonel in charge of civilian protection for Nassau County to request that the Army guard the power station.[6]
The two units of Station 3 became operational in 1952 and 1954.[7] At the time The New York Times called it "one of the most modern power plants in the country," with both mechanical and electrostatic precipitators for dust and ash collection, as well as valve silencers and noise barriers. It was the first turbine generator mounted on an open deck in the Northeastern United States. Two similar units were constructed about the same time on the South Shore in the new Far Rockaway Power Station and E. F. Barrett Power Station.[8]
In 1967, a 15 MW GE Frame 5 gas turbine generator was constructed for black start, peaking, and emergency purposes.[9]
In 1972, the Town of Oyster Bay board unanimously denied LILCO a permit to further expand the plant with five 50 MW gas turbines, citing air-quality concerns and the effects of the 1970s energy crisis. Town Supervisor John W. Burke at the time noted the board's recognition that "in view of the fuel shortage, construction of gas turbines just seems out of step with the direction being taken by the average consumer, who lowers his thermostat and wears a sweater in his home to reduce the amount of fuel burning."[10] Nevertheless, two GE Frame 7B gas turbine generators were constructed that year.[9]
In 1978, the Y-50 Cable was constructed between Westchester County's Dunwoodie North Substation and the Glenwood Generating Station, via the Long Island Sound.[11][12][13]
Continued operation
[edit]The Station 2 generating units were taken out of operation in 1978,[14] but as late as 2009 the building was used for such purposes as a waste water treatment facility for the adjacent operational units, office and warehouse space, and transmission and fiber optic lines.[15]
In 1998, as part of a state-brokered deal, LILCO's power generation facilities, including the Glenwood plant, were absorbed into KeySpan Energy, with the public Long Island Power Authority (LIPA) taking over transmission and delivery functions.[16][17] KeySpan would be acquired by National Grid in 2007.[18]
In 2001, LIPA proposed building two mini-turbines at Glenwood Landing as part of a plan to build ten such plants across Long Island to avoid the risk of rolling blackouts in the face of increased demand like those experienced in California the previous year, given strain on the system from a heat wave in 2001. The pair of turbines produced 79 MW, just under an 80 MW threshold that would have triggered a full regulatory and environmental review.[19][20][21] The new turbines were completed by May 2002, and were the first of the ten to enter operation.[22][23]
Station 3's utilization decreased from 43 percent in 2001 to 11.2 percent in 2005. As of 2009, the power station was used as a peaking power plant operating in the summer, with two operational natural gas steam-electric generating units with a combined 210 MW capacity. It had a once-through water cooling system using water from the adjacent Hempstead Harbor.[15] By 2014 the Station 2 building had deteriorated to the point where it was nearing condemnation.[14]
Demolition of steam plants
[edit]In 2011 it was announced that the Glenwood Landing station would be shut down and demolished along with its sister plant in Far Rockaway. The two stations were described as the oldest and least efficient of the power plants on Long Island, with the closures saving $76 million through 2015.[24]
Local resident Karin Barnaby campaigned to renovate Station 2 for commercial and cultural uses rather than demolish it, pointing to other redeveloped historic power plants in the United States such as the Pratt Street Power Plant in Baltimore and the Homan Square Power House in Chicago.[25] Despite collecting 780 signatures for a petition, this was rejected due to the excessive cost of renovating the building given its poor condition.[14] Demolition was estimated to cost $8 million, as opposed to $31 million to make the building structurally sound without improving it, and $100 million to renovate it into a mixed-use development including an exhibition hall in the old turbine room. Using the building for new power generation capacity was deemed unfeasible because modern generation equipment was incompatible with the building design.[2]
Demolition of the plant raised concern about the financial effects on the local North Shore School District, as the over $20 million annual tax payments from the plant provided 20 percent of the district's budget.[4] This led to fears of a 15–19% increase in residential taxes in late 2014. However, it was determined that according to state law there could be no more than a 1% increase in property taxes for a given tax class as a result of a decreased tax assessment in another class (the four tax classes being residential, cooperatives/condominiums, commercial, and utilities). The financial effects on the district would thus have to be mitigated by increased taxes on remaining utilities in the district, as well as a $2.5 million one-time grant from the state arranged by local state legislators.[26][27] The site's municipal and school payments in lieu of taxes fell from $23.2 million in 2012 to $16.6 million in 2015.[28]
Station 3 was demolished in November 2013, and demolition of Station 2 was completed in 2015. National Grid opted for a controlled deconstruction rather than an implosion or using a wrecking ball.[14] The demolition of Station 2 required the relocation of a peregrine falcon nest from the top of one of the smoke stacks.[1] After demolition and land remediation had been completed, the area was planned to be paved over with asphalt and offered to developers.[14]
Later history
[edit]The three smaller gas-turbine peaking generators built by LILCO in 1967 and 1972 remained in operation,[9] as did the two constructed in 2002.[29] In addition, three electrical substations, three fuel tanks, and a water tower elsewhere on the site remained in operation.[1][14]
In 2017, National Grid proposed raising the legal power output limit of the two 2002 peaking plants from 79.9 MW to 94 megawatts.[29] In 2020, the 15 MW generator from 1967 was shuttered, leaving four more operational,[30] and the two 1972 generators had water injection systems installed, to comply with stricter air emissions regulations.[31] As of 2020, Glenwood Generating Station's remaining 232 MW nameplate capacity made it the eighth largest power generation facility on Long Island. That year it generated 107.7 GWh, which placed twelfth.[32]
See also
[edit]References
[edit]- ^ a b c d e f "Glenwood Overhead 69 KV Transmission Line Relocation and Glenwood Power Station Decommissioning and Demolition Project: Environmental Impact Assessment" (PDF). Long Island Power Authority. June 2012. pp. 1–9, 6–1, 6–2, 9–1, 9–2. Archived (PDF) from the original on 9 December 2014. Retrieved 4 December 2014.
- ^ a b c d e "Alternative Use Analysis: Glenwood Power Station No. 2". Louis Berger Group, Inc. 25 June 2012. pp. i, 9–30. Archived from the original on 5 June 2021. Retrieved 4 December 2014. (Document starts on page 27 of file.)
- ^ a b c "Historic American Buildings Survey/Historic American Engineering Record Level 1 Report". April 2013. pp. 7–14. Archived from the original on 5 June 2021. Retrieved 4 December 2014. (Document starts on page 153 of file.)
- ^ a b Rumsey, Spencer (3 March 2014). "Power Plant Closures Generate Taxing Troubles". Long Island Press. Archived from the original on 9 December 2014. Retrieved 4 December 2014.
- ^ "Power Line Break Halts War Plants: Electricity Cut Off 1 to 2 Hours in Nassau, Suffolk Counties on Long Island". The New York Times. 20 August 1942. p. 21. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ "Asks Guard For Utility: Nassau Defense Head Calls on Army to Protect Power Plant". The New York Times. 1 September 1942. p. 13. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ "ENB Region 1 Completed Applications". New York State Department of Environmental Conservation. 11 January 2006. Archived from the original on 2016-09-19. Retrieved 3 December 2014.
- ^ "Long Island Lighting Opens Big Power Unit As First Step in 50 Million Expansion Plan". The New York Times. 28 November 1952. p. 35. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ a b c Rodriguez, Raul R. (2015-06-26). "Survey of National Grid Generation Formerly Owned By LILCO" (PDF). U.S. Environmental Protection Agency. pp. 3, 15. Archived (PDF) from the original on 2021-05-22. Retrieved 2021-05-21.
- ^ Silver, Roy R. (20 March 1974). "Oyster Bay Rejects LILCO Bid To Expand a Generating Station; special to The New York Times". The New York Times. p. 27. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ "LIPA and Con Edison Put Y50 Cable Back In Service". Power Quality Magazine. 2002-07-01. Archived from the original on 2022-01-20. Retrieved 2022-03-23.
- ^ Harrington, Mark (2021-04-12). "NYPA cable between LI, Westchester has been 'unreliable' for months, LIPA chief says". Newsday. Archived from the original on 2022-03-23. Retrieved 2022-03-23.
- ^ Harrington, Mark (2021-08-11). "LIPA discloses two new major power line failures". Newsday. Archived from the original on 2021-08-21. Retrieved 2021-08-21.
- ^ a b c d e f "At meeting with NS residents, National Grid outlines plans for Glenwood Landing property and tax assessments". North Word News. 25 January 2014. Archived from the original on 7 December 2014. Retrieved 4 December 2014.
- ^ a b Kimble, C. (July 2009). "Biological Fact Sheet - Cooling Water Intake Structure" (PDF). New York State Department of Environmental Conservation. Archived from the original (PDF) on 2014-12-19. Retrieved 4 December 2014.
- ^ Lambert, Bruce (28 May 1998). "The End of Lilco, as Long Island Has Come to Know It". The New York Times. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ Rather, John (9 October 2005). "Power Couple". The New York Times. Retrieved 4 December 2014.
- ^ Rather, John (1 April 2007). "LIPA, National Grid and KeySpan Reach Deal". The New York Times. Archived from the original on 5 June 2015. Retrieved 4 December 2014.
- ^ Gootman, Elissa (19 October 2001). "Proposed Mini-Plants Are Part Of a Long-Term Energy Plan". The New York Times. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ Rather, John (17 March 2002). "LIPA Is Adding Juice But Is Still Thirsty". The New York Times. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ McGinty, Tom (2001-10-19). "Watts up for LIPA next year". Newsday. p. 55. Retrieved 2022-10-16.
- ^ Gootman, Elissa (30 May 2002). "Official Says L.I. Should Have Plenty of Electricity This Summer". The New York Times. Archived from the original on 10 December 2014. Retrieved 4 December 2014.
- ^ Solnik, Claude (2002-08-02). "PPL Global turns power switch at Shoreham". Long Island Business News. Archived from the original on 2021-05-22. Retrieved 2021-05-22.
- ^ Famiglietti, Charleen (16 June 2011). "LIPA, National Grid to Shut Down Glenwood Power Station". Glen Cove Patch. Archived from the original on 8 December 2014. Retrieved 4 December 2014.
- ^ Barnaby, Karin (20 February 2014). "Barnaby: Give new life to the Glenwood Landing plant". Newsday. Archived from the original on 14 December 2014. Retrieved 4 December 2014.
- ^ "BOE expresses uncertainty regarding potential tax shift from decommissioning of Glenwood Landing power plant". North Word News. 20 January 2014. Archived from the original on 7 December 2014. Retrieved 4 December 2014.
- ^ "Examining Glenwood Plant Details". Glen Cove Record Pilot. 19 December 2013. Archived from the original on 9 December 2014. Retrieved 4 December 2014.
- ^ Harrington, Mark (2016-02-13). "Long, slow fight by LIPA against property taxes". Newsday. Archived from the original on 2016-08-08. Retrieved 2016-06-13.
- ^ a b Harrington, Mark (2017-03-22). "Grid wants to raise output at 2 small plants". Newsday. Archived from the original on 2021-05-20. Retrieved 2021-05-20.
- ^ Harrington, Mark (2020-03-02). "LIPA to close 2 small power plants in Nassau, Suffolk". Newsday. Archived from the original on 2021-05-20. Retrieved 2021-05-20.
- ^ Anderson, Jared (2020-04-07). "Nearly 650 MW of New York City peaking capacity will retire to comply with tighter regulations". S & P Global. Archived from the original on 2022-03-25. Retrieved 2022-03-25.
- ^ "Gold Book: 2021 Load & Capacity Data". New York Independent System Operator. 2021-04-01. pp. 77–99. Archived from the original on 2022-03-08. Retrieved 2022-03-22.
External links
[edit]- Supplemental Environmental Impact Assessment for Glenwood Power Station Decommissioning and Demolition Archived 2021-06-05 at the Wayback Machine - Contains many contemporary and historical photographs of the plant's interior and exterior
- Last Days of the Glenwood Landing Power Station[permanent dead link ] - A gallery of photographs of the power station
- Natural gas-fired power stations in New York (state)
- Demolished power stations in the United States
- Energy infrastructure completed in 1906
- Energy infrastructure completed in 1923
- Energy infrastructure completed in 1954
- Energy infrastructure completed in 2002
- Long Island Sound
- 1906 establishments in New York (state)
- Former power stations in New York (state)
- Energy infrastructure on Long Island, New York