Jump to content

Dandenong Bypass

From Wikipedia, the free encyclopedia

Dandenong Bypass

Dandenong Bypass is located in Melbourne
West end
West end
East end
East end
Coordinates
General information
TypeHighway
Length8.1 km (5.0 mi)[1]
Opened2007–2012
Route number(s) Metro Route 49 (2012–present)
(through Keysborough)
Major junctions
West end Westall Road
Keysborough, Melbourne
 
East end South Gippsland Highway
Dandenong South, Melbourne
Location(s)
Major settlementsKeysborough
Highway system

The Dandenong Bypass is a highway in the state of Victoria, Australia that runs along the Dingley Freeway reservation from Springvale Road in Keysborough to the South Gippsland Highway in Dandenong South.

History

[edit]

The Dandenong Bypass was completed along the alignment reserved for the Dingley Freeway corridor, staged in two separate projects over seven years. The entire bypass has a speed limit of 80 km/h with traffic light controlled intersections and overpasses at Cheltenham Road and EastLink.

Dandenong Bypass was signed as Metropolitan Route 49 between Springvale Road and EastLink through Keysborough, when the second stage of the bypass was opened in 2012.

The passing of the Road Management Act 2004[2] granted the responsibility of overall management and development of Victoria's major arterial roads to VicRoads: in 2007, VicRoads re-declared Dandenong Bypass (Arterial #6420) from Perry Road in Keysborough to South Gippsland Highway in Dandenong South;[3] the declaration has since been extended to cover Stage 2 of the bypass terminating at Springvale Road in Keysborough.[4]

Stage 1: Perry Road to South Gippsland Highway

[edit]

The first stage of the bypass commenced construction in late 2005 between Perry Road and South Gippsland Highway as part of the EastLink project, with the $65 million works involving the creation of a four lane divided road with traffic light controlled access at roads which run north-south along the constructed route.

The 4.8 km bypass also included an overpass of the Cranbourne railway line as well as a diamond interchange with EastLink. The entire bypass has an 80 km/h speed limit. The project was completed and opened to traffic on 9 December 2007.[5]

Stage 2: Springvale Road to Perry Road

[edit]

The second stage of the bypass commenced construction in 2011 between Springvale Road and Perry Road, connecting the existing Dandenong Bypass at Perry Road with Westall Road and creating an arterial-standard highway, with traffic light controlled intersections and an overpass at Cheltenham Road, for 11 km from Heatherton Road in Springvale to the South Gippsland Highway.[6]

The new section of road was expected to carry between 30,000 and 40,000 vehicles per day, and also included a shared path being constructed alongside, linking to existing shared paths along the previously-built section of the arterial. The construction of this section (at a cost of $74.6 million) was brought forward to commence in 2010 as part of the "Nation Building" initiatives in the 2009 Victorian State Budget.[7] The project was completed early and under budget (previously estimated to cost $80 million) to traffic on 20 December 2012.[8][9]

Intersections

[edit]

Dandenong Bypass is entirely contained within the City of Greater Dandenong local government area.

Location[1][3][4]km[1]miDestinationsNotes
Keysborough0.00.0 Westall Road (Metro Route 49) – Springvale SouthWestern terminus of road; Metro Route 49 continues north-west as Westall Road
Springvale Road (Metro Route 40) – Edithvale, Springvale
2.31.4Chapel Road – Keysborough, Noble Park
3.32.1Perry Road – Keysborough, Bangholme
3.92.4Chandler Road – Keysborough, Noble Park
4.93.0 EastLink (M3) – Melbourne, Ringwood, FrankstonDiamond interchange
Eastern terminus of Metro Route 49 (signed)
Dandenong South6.33.9Hammond Road – Dandenong, Dandenong South
7.14.4 Frankston-Dandenong Road (Metro Route 9) – Frankston, Dandenong
7.94.9Cranbourne railway line
8.15.0 South Gippsland Highway – Dandenong, Cranbourne, Phillip IslandEastern terminus of road
1.000 mi = 1.609 km; 1.000 km = 0.621 mi
  •       Route transition

See also

[edit]

References

[edit]
  1. ^ a b c "Dandenong Bypass" (Map). Google Maps. Retrieved 24 November 2021.
  2. ^ State Government of Victoria. "Road Management Act 2004" (PDF). Government of Victoria. Archived (PDF) from the original on 18 October 2021. Retrieved 19 October 2021.
  3. ^ a b VicRoads. "VicRoads – Register of Public Roads (Part A) 2015" (PDF). Government of Victoria. p. 784. Archived from the original on 1 May 2020. Retrieved 19 October 2021.
  4. ^ a b VicRoads. "VicRoads – Map of Declared Roads". Government of Victoria. Retrieved 24 November 2021.
  5. ^ EastLink tollway to open six months early Herald Sun 10 December 2007. Retrieved on 12 December 2007.
  6. ^ "Dingley Arterial - Keysborough : VicRoads". Archived from the original on 21 March 2012. Retrieved 20 June 2013.
  7. ^ Gren Light for $74.6 Million Dingley Arterial Project Archived 13 July 2009 at the Wayback Machine Retrieved on 7 May 2009.
  8. ^ "The Victorian Transport Plan: Dingley Arterial". Archived from the original on 15 September 2009. Retrieved 20 June 2013.
  9. ^ "VicRoads Annual Report 2012-13". VicRoads. Melbourne: Victorian Government Library Service. 27 August 2012. p. 18.