Talcher Super Thermal Power Station
It has been suggested that this article be merged into NTPC Limited. (Discuss) Proposed since September 2024. |
Talcher Super Thermal Power Station | |
---|---|
Country | India |
Coordinates | 21°5′18″N 85°4′50″E / 21.08833°N 85.08056°E |
Status | Operational |
Commission date | February 1995 |
Owner | NTPC |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Units operational | 6 × 500 MW |
Make and model | ABB BHEL |
Nameplate capacity | 3,000 MW |
External links | |
Website | www |
Talcher Super Thermal Power Station or NTPC Talcher Kaniha located in Angul district of the Indian state of Odisha is the first mega power plant of India to have an installed generation capacity of 3000MW. The power plant is one of the coal-based power plants of NTPC. The coal for the power plant is sourced from Lingraj Block & Kaniha coal block of Mahanadi Coalfields Ltd. Source of water for the power plant is from Samal Barrage Reservoir on Brahmani River.
The plant supplies power to Indian states of Odisha, Andhra Pradesh, Karnataka, Telangana as well as Bihar and West Bengal. The East South Interconnection of the Indian power grid starts from NTPC kaniha and ends at Kolar in Karnataka. This being a DC link is one of its kind in India as uptill now there are only 3 installed HVDC system present in India. The Southern grid is weakly interconnected to the National grid of India through the Talcher-Kolar HVDC system in the East.
Capacity
[edit]Stage | Unit number | Installed capacity (MW) | Date of commissioning |
---|---|---|---|
1st | 1 | 500 | 1995 February |
1st | 2 | 500 | 1996 March |
2nd | 3 | 500 | 2003 January |
2nd | 4 | 500 | 2003 October |
3rd | 5 | 500 | 2004 May |
3rd | 6 | 500 | 2005 February |
Total | Six | 3000 |
See also
[edit]- Talcher Thermal Power Station, another coal-based power plant in close vicinity which was taken over by NTPC from Odisha State Electricity Board in June 1995.