Madhya Pradesh Power Generation Company Limited
Appearance
(Redirected from M.P. Power Generation Company Limited)
Company type | Government-owned Corporation-PSU |
---|---|
Industry | Electricity generation |
Founded | The Company was incorporated on 22.11.2001 & started functioning independently from 01-06-2005 |
Headquarters | Jabalpur, Madhya Pradesh, India |
Area served | State of Madhya Pradesh,India |
Key people | Shri Sanjay Dubey (chairman) Shri Manjeet Singh (managing director) |
Services | Electricity Generation |
Owner | Government of Madhya Pradesh (100%) |
Number of employees | 4878 |
Website | www |
M.P. Power Generating Company Limited (MPPGCL) is the electricity generation company of the Government of Madhya Pradesh state in India.
Generation capacity
[edit]The installed capacity of MPPGCL as on 01.01.2019 is 6315 MW out of which madhya pradesh share is about 6312.50 MW.[1]
PLF (%) LAST 10 YEARS | |||||
YEARS | ATPS | STPS | SGTPS | SSTPP | OVERALL |
2009-10 | 45.89% | 64.57% | 65.99% | N.A. | 62.86% |
2010-11 | 48.66% | 60.51% | 65.78% | N.A. | 61.10% |
2011-12 | 54.66% | 53.68% | 70.20% | N.A. | 61.38% |
2012-13 | 71.66% | 55.26% | 73.52% | N.A. | 66.24% |
2013-14 | 74.3% | 48.0% | 67.8% | N.A. | 60.0% |
2014-15 | 53.3% | 52.9% | 58.1% | 26.23% | 49.6% |
2015-16 | 96.8% | 47.2% | 59.9% | 40.4% | 51.2% |
2016-17 | 80.51% | 31.28% | 58.53% | 23.54% | 40.49% |
2017-18 | 93.94% | 43.09% | 64.26% | 35.90% | 50.55% |
2018-19 | 88.9% | 64.1% | 74.0% | 61.1% | 67.3% |
Power stations
[edit]Thermal power stations coal based
[edit]Sr.No | Project | Capacity(in M.W.) | Unit MW | Status | EPC Contractor(TG set and Boiler make) |
---|---|---|---|---|---|
1 | Satpura Thermal Power Station | 1330 | 1×200 MW, 3x210 MW, 2x250 MW | All Unit Functional,however 200MW and 210 MW to be decommissioned soon ,1x660 MW under surveying | BHEL |
2 | Amarkantak Thermal Power Station | 210 | 1×210 MW | All Unit Functional ,1x660 MW under surveying | BHEL |
3 | Sanjay Gandhi Thermal Power Station | 1340 | 4×210 MW,1×500 MW | All Unit Functional | BHEL(though ABL make boiler in 210MW units) |
4 | Shree Singaji Thermal Power Station | 2520 | 2x600 MW, 2×660 MW(super critical) | All Unit Functional. | BHEL -600MW, L&T-MHPS-660MW |
Total installed thermal capacity 5400 MW.
Hydel power stations
[edit]Sr.No | Power Station | Installed Capacity | M.P.Share | LOCATION/ RIVER | ||||
---|---|---|---|---|---|---|---|---|
1 | Gandhi Sagar(5x23 MW) | 115 | 57.5 | DISTT. MANDSOUR/ CHAMBAL RIVER | ||||
2 | Pench,Totladoh(2x80 MW) | 160 | 107 | DISTT. NAGPUR/ PENCH RIVER | ||||
3 | Rani Awanti Bai Bargi (2x45 MW) | 90 | 90 | BARGI, DISTT. JABALPUR/ NARMADA RIVE | ||||
4 | Rajghat (3x15 MW) | 45 | 22.5 | RAJGHAT, DISTT. ASHOKNAGAR/ BETWA RIVER | ||||
5 | Birsinghpur(1x20 MW) | 20 | 20 | BIRSINGHPUR, DISTT. UMARIYA/ JOHILA RIVER | ||||
6 | Ban Sagar I Tons(3x105 MW) | 315 | 315 | SIRMOUR, DISTT. REWA BEEHAR RIVER | ||||
7 | Ban Sagar II Silpara(2x15 MW) | 30 | 30 | SILPARA, DISTT. REWA/ CANA | ||||
8 | Bansagar -III Deolond (3x20 MW) | 60 | 60 | DEOLOND, DISTT. SHAHDOL/ SONE RIVER | ||||
9 | Bansagar -IV Jhinna (2x10 MW) | 20 | 20 | JHINNA, DISTT. SATNA/ JHINNA DYKE | ||||
10 | Madhikheda (3x20 MW) | 60 | 60 | MADHIKHEDA, DISTT. SHIVPURI/ KALISINDH RIVER | Total | 1186 | 917.5 |
Two proposed Hydel unit at Chhindwara(2x45MW) and Murena(270 MW)